HUD 2018 RAD Closing Timelines

HUD established timelines for fourth quarter RAD closings in order to plan for the Office of Recapitalization’s workload and necessary approvals. The table below indicates when items must be complete in order to close in 2018. This memo provides additional information about how HUD will prioritize projects when transaction volume exceeds their processing capacity.

ActionNovember 30 ClosingDecember 31 Closing
Upload all required Financing Plan documentsJune 15July 13
Receive a HUD-executed RCCAugust 17September 14
Submit a complete closing packageSeptember 1October 1
All RAD documents approved and ready for HUD signaturesNovember 15December 13